year 2001 marked another milestone for Thailand's transport sector,
as the passenger terminal and concourse of the long-awaited Suvarnabhumi
International Airport finally got off the ground, raising hopes
that the airport would be completed by the end of 2004.
The construction
of the 36.67-billion-baht main passenger terminal and concourse
started on Dec 1 and is expected to be finished in three years.
 |
|
The aborted Hopewell project contrasts
with plans for a nationwide dual-track system that is estimated
to cost at least 214 billion baht. |
Italian-Thai
development with its Japanese partners, Takenaka Corp and Obayashi
Corp, signed the deal with New Bangkok International Airport
Co (NBIA) on Nov 9.
The terminal
will be capable of handling 36 million passengers a year.
The project
had been on a roller-coaster ride throughout the year, with
sporadic disputes between the Thai government and the project's
major financial sponsor, the Japan Bank for International Co-operation
(JBIC).
The Japanese
government had threatened to withdraw its financing commitments
to the airport, shortly after it had frozen a one-billion-baht
loan for piling work at the site. The threat came after the
Thai government authorised the piling work without waiting for
JBIC's approval.
The terminal
project, meanwhile, had been a political football for years,
with frequent squabbles over the design, which the government
maintained was too costly and relied too heavily on imported
materials.
The initial
price had been set at 48 billion baht, but after a redesign
NBIA declared a median price of 36.78 billion baht. The Italian-Thai
group was the only bidder among three contenders to come in
under the median price. It also said that 81% of the construction
materials and labour would be sourced locally.
The JBIC
has agreed to lend all the money needed for the project, at
0.75% interest.
No sooner
had construction begun, however, than the airport development
committee said it would ask NBIA to expand the terminal to cater
for up to 43 million passengers a year. The development company
would be asked to seek another six billion baht from JBIC for
the expansion.
The government
is also pushing to develop multi-billion-baht expressway projects
to service the new airport.
One proposed
project is a 4.7-km link to connect the Bang Na-Chon Buri expressway
with the first- and second-stage expressways, as well as the
Ram Intra-Art Narong expressway. The Expressway and Rapid Transit
Authority estimated the cost of the links at 3.6 billion baht,
which the Interior Ministry said was too high.
Another
project under consideration is a one-kilometre ramp linking
the Bang Na-Chon Buri expressway with the airport, costing one
billion baht.
Meanwhile,
the State Railway of Thailand is also pressing hard to develop
a rail route linking Bangkok with Suvarnabhumi airport.
 |
|
Prime Minister Thaksin examines a
model of the Suvarnabhumi airport terminal, which will cost
36.7 billion baht. |
According
to a study by Pacific Consultants International, the 20-km Phaya
Thai-Makkasan-Hua Mark-Suvarnabhumi rail link is a vital part
of the infrastructure required to serve the airport, as well
as provide a transport alternative to tackle traffic problems.
The rails
would be elevated to avoid creating crossroads that could cause
traffic congestion, and electric-powered trains would operate
on the line.
Construction
of the new rail route was expected to start early in 2002 and
take two years to complete.
The elevated
link would connect with the underground train system at Makkasan
and the BTS skytrain network at the Phaya Thai station.
The project
would be financed by the state budget and loans.
Concessions
may be granted to the private sector to operate the trains and
terminals, but this was up to the cabinet.
Moreover,
the rail agency is pushing for cabinet consideration of a nationwide
dual-track system worth more than 214 billion baht.
The system
would not only improve rail safety and efficiency, but would
also promote the SRT's plan to increase freight services to
shore up revenues.
The SRT
has been working on two double-tracking projects spanning 234
kilometres.
The first
leg, 61 km from Klong Rangsit Station to Ban Phachi junction
in Ayutthaya, cost 3.2 billion baht.
It was completed
in October 1999 and a traffic-control system is now being installed.
The second
part consists of four legs: 45 km from Hua Mark to Chachoengsao
(six billion baht); 41 km linking Taling Chan and Nakhon Pathom
(4.46 billion); 44 km from Ban Phachi to Map Kaboa in Sara Buri
(2.39 billion); and 43 km from Ban Phachi to Lop Buri (2.05
billion baht).
Section
one of the second project is due to be completed in March 2003,
with the other three sections to be completed in July of 2002.
Elsewhere
in mass transit, the aborted Hopewell elevated rail and road
project has gone back to the drawing board.
Prime Minister
Thaksin Shinawatra had earlier rejected reviving the project,
which the government forecast would cost 30 billion baht in
state funds.
But the
government later relented and decided to consider completing
the project but on a smaller scale.
The Office
of the Commission for the Management of Land Traffic (OCMLT)
has been assigned to hire a consultant to study investment costs
and new construction patterns, and set terms for choosing contractors.
Under the
Transport and Communications Ministry's revised plan, the state
would use Hopewell's concrete pillars to develop a 20-km elevated
railway from Bang Sue to Don Muang.
 |
|
Buses remain the main mode of transport
for the cash-strapped masses. |
The scheme
would cost between nine billion and 12 billion baht and ease
traffic congestion.
The Bang
Sue railway station would be developed into a new terminal to
take over the northern, northeastern and southern trains from
Hua Lamphong, which would service only eastern trains.
The ministry
has set a deadline of Jan 31 to finalise details of the project.
Mass transit
via the Bangkok Mass Transit System (BTS) skytrain has also
begun to grow more popular.
It now carries
an average of 250,000 commuters a day, up from 150,000 a day
in 2000.
However,
the total is much lower than the 400,000 projected originally,
a level that would cover the company's operating costs and interest
payments.
The current
number of passengers generates only enough revenue to cover
daily operations, including wages, electricity and maintenance.
The skytrain
is currently earning between four million and five million baht
a day from fares, up from three million baht a year ago.
"The number
of commuters is improving. We expect passengers will reach 300,000
a day at the end of 2001 and touch 350,000 in 2002, as people
are becoming familiar with commuting by skytrain," said Anant
Arbhabhirama, adviser to BTS.
Extending
the skytrain route, with one leg crossing the Chao Phraya River,
is also expected to improve the system's potential.
The OCMLT
will soon hire an advisory firm to conduct a feasibility study
on the extension project.
An earlier
proposal for the skytrain extension had been turned down by
a state panel, which argued that it went against a cabinet decision
favouring 100% private investment in any new lines.
The cabinet
wanted the system extended on three fronts: three kilometres
from Sathon to Phetkasem, eight kilometres from Onnuj to Samrong,
and eight kilometres from Chong Nonsi to Rama III road.
But BTS
wanted to take on only two routes: Sathon-Phetkasem and Onnuj-Samrong.
The company had also asked the state to invest in civil construction
work.
City commuters
will also have to wait a little longer to ride on the country's
first subway system.
The partial
opening of the subway, the Hua Lamphong-Huay Khwang route, scheduled
for completion late in 2002, was likely to be delayed due to
the delay in signing a contract to purchase carriages and operating
systems worth nearly 18 billion baht.
Under the
25-year concession contract, Bangkok Metro Co Ltd was required
to have signed contracts with train suppliers by May 2001, with
delivery to be made within 18 months.